What is the waiting period for the production of entrance doors?
The waiting time for external doors may vary depending on the material they are made of. For example, PVC external doors require approximately 6 weeks of waiting time, while aluminum doors require approximately 8 weeks. If you want wooden doors, you must be prepared for a longer waiting period, which is approximately 12 weeks. However, if you are interested in steel doors, the waiting time is also about 6 weeks. When choosing external doors, it is worth considering not only the material, but also availability and waiting time to adapt renovation or construction plans to this schedule.
Production waiting period:
Exterior vinyl doors : 6 weeks
Exterior aluminum doors : 8 weeks
External wooden doors: 12 weeks
External steel doors: 6 weeks